Tacoma Hydraulics
July to October 2020 (4-month turnaround)
The scope of work consisted of corrosion protection of all hydraulic cylinders, deck winches, large winch drum, boom, and associated parts. Coast Guard crew was at our shop daily checking blast profiles, coating thickness, and overall inspection of the parts we worked on.
Precision Iron Works – Amazon Project Beige
March to July 2021 (5-month turnaround)
Sandblasted and painted over 1500 pieces of perimeter, stair and guard rails in Safety Yellow. We also worked on stair stringers, mezzanines and support columns.
B & B Fabricators
August to December 2021 (5-month turnaround)
The scope of the work consisted of sandblasting and priming HSS Frames, canopies, and mechanical equipment screens that were installed at the Costco Headquarters.
Alliance Steel Fabricators
December 2020 to March 2022
Bench frames, screen frames, rail posts, fence posts, structural steel, perforated panels, and stairs – three-coat high-performance coating.
A & B Fabricators
October 2020 to April 2022
Bench frames, screen frames, rail posts, fence posts, structural steel, perforated panels, and stairs – three-coat high-performance coating.
Skyline Steel
October 2020 (1-month turnaround)
Sheet Pile – sandblast and paint with a high-performance marine paint system.
Skyline Steel
November 2020 to June 2021 (8-month turnaround)
Sandblast and paint with a three-coat system, the third coat being in the wave zone.
McKinstry Company
November 2021 to April 2022 (6-month turnaround)
Sandblast and paint high-performance three-coat system to tables, frames, and platforms.
WHECO Corp.
July to August 2021 (2-month turnaround)
We removed all existing failing coatings via sandblasting. Once parts were sandblasted, WHECO fixed damaged welds. Once received back we sandblasted, followed by a three-coat high-performance coating system.
Standard Steel Fabricating Company
December 2021 to January 2022 (2-month turnaround)
This was a new construction bus shelter roughly 5,200 sqft. We sandblasted and applied a three-coat coatings system – zinc primer, epoxy mid-coat, polyurethane top-coat.
AAA Welding
November 2021 (1-month turnaround)
Three-section pedestrian bridge – we sandblasted and primed with a zinc primer, then the bridge was top-coated in the field after installation by others.
MBI Construction Services
February to April 2022 (3-month turnaround)
Pipe stanchions for light rail track and walkway – sandblasted and coated per the Sound Transit high-performance coating system #2.